What does this study process involve?
Below are links to a presentation given to the task force on the I-75/I-475 Major Project Design Activities in
ODOT's new 14-Step Project Development Process (PDP).
.ppt version
.pdf version
| Step |
Date |
Description |
| 1 |
1996
thru 2002 |
-Expressway Needs Study commissioned
by TMACOG
-I-75/I-475 recognized as
a priority area
-Commissioned Access Modification Study
-Began
I-75/I-475 public involvement meetings
-Determined specific goals
|
| 2 |
2002/
2003 |
-Conduct
research and technical studies on existing and future conditions
|
| 3 |
2002 |
-Identified conceptual alternatives
-Weighed costs/benefits/impacts
|
| 4 |
2002 |
-Presented
conceptual alternatives to stakeholders
|
| 5 |
2003 |
-Start environmental field studies
-Continue holding public involvement meetings
|
| 6 |
2002
thru 2005 |
-Evaluate feasible alternatives
-Determine preferred alternative
-Complete environmental field studies
-Hold final public involvement meetings
|
| 7 |
2006/
2007 |
-Conclude Access Modification Study
-Complete environmental document
|
| 8 |
2006/
2007 |
-Begin final design
-Establish
construction limits
-Submit
Stage 1 Detailed Design
|
| 9 |
2007 |
-Prepare
preliminary right-of-way plans showing all takes
-Develop
design plans showing all engineering details
-Submit
Preliminary Right of Way
-Submit
Stage 2 Detailed Design
|
| 10 |
2008
|
-Prepare
final right-of-way plans and legal descriptions
-Submit
Final Right of Way
-Submit
Right of Way Tracings
|
| 11 |
2008 |
-Quantify
all pay items
-Detail
all proposed construction
-Submit
Stage 3 Detailed Design
|
| 12 |
2008 |
-Prepare
supplementary info. needed to sell plans
-Submit
Final Tracings
|
| 13 |
2008 |
-Assist
with pre-bid questions
|
| 14 |
2009 |
-Attend
pre-construction meeting
-Answer
design questions that arise during construction
-Attend
post-construction meeting
|
|