What does this study process involve?
date posted: 12.21.2006

Below are links to a presentation given to the task force on the I-75/I-475 Major Project Design Activities in ODOT's new 14-Step Project Development Process (PDP).
.ppt version
.pdf version
Step Date Description
1 1996 thru 2002

-Expressway Needs Study commissioned by TMACOG

-I-75/I-475 recognized as a priority area

-Commissioned Access Modification Study

-Began I-75/I-475 public involvement meetings

-Determined specific goals

2 2002/ 2003

-Conduct research and technical studies on existing and future conditions

3 2002

-Identified conceptual alternatives
-Weighed costs/benefits/impacts

4 2002

-Presented conceptual alternatives to stakeholders

5 2003

-Start environmental field studies

-Continue holding public involvement meetings

6 2002 thru 2005

-Evaluate feasible alternatives
-Determine preferred alternative

-Complete environmental field studies
-Hold final public involvement meetings

7 2006/ 2007

-Conclude Access Modification Study

-Complete environmental document

8 2006/ 2007

-Begin final design

-Establish construction limits

-Submit Stage 1 Detailed Design

9 2007

-Prepare preliminary right-of-way plans showing all takes

-Develop design plans showing all engineering details

-Submit Preliminary Right of Way

-Submit Stage 2 Detailed Design

10

2008

-Prepare final right-of-way plans and legal descriptions

-Submit Final Right of Way

-Submit Right of Way Tracings

11 2008

-Quantify all pay items

-Detail all proposed construction

-Submit Stage 3 Detailed Design

12 2008

-Prepare supplementary info. needed to sell plans

-Submit Final Tracings

13 2008

-Assist with pre-bid questions

14 2009

-Attend pre-construction meeting

-Answer design questions that arise during construction

-Attend post-construction meeting


 
 
  